FERNANDINA BEACH — Bids for the demolition of Brett's Waterway Cafe and reconstruction of a key section of the city marina will be opened July 2, with construction tentatively scheduled to begin Aug. 10, Deputy City Manager Glenn Akramoff told the Waterfront Advisory Board on Monday.
Following the July 2 bid opening, city commissioners will hold a workshop July 7 to review bid results, discuss funding options and receive a detailed briefing on project phasing and anticipated construction schedules.
The city has received strong interest from contractors. Akramoff said 28 representatives attended the pre-bid meeting, filling the room and generating extensive questions about the project's 385-page bid package.
Even so, Akramoff cautioned that residents should be prepared for a significant price tag.
One of the city's primary objectives is keeping the marina functioning during construction.
The city is also planning ahead for a future marina building. Akramoff said engineers have designed the new pier to be capable of supporting a structure if commissioners later decide to construct a marina store or operations center on the site.

Akramoff said maintaining access to marina facilities has been a central focus during project planning.
"Staging is super important," Akramoff said.
The city has established a four-to-eight-week window during which fuel operations could be shut down, although officials hope to keep the outage closer to four weeks.
"We told them no more than 24 hours," Akramoff said, referring to utility outages serving marina tenants and boaters.
The most visible phase of the project will likely occur in September when demolition crews are expected to begin dismantling the former Brett's Waterway Cafe building, a longtime downtown landmark that once served as a major attraction for visitors and residents alike.
Because of the waterfront location, most demolition debris and construction materials will be transported by barge rather than through downtown streets. Akramoff said the city wants to minimize truck traffic and reduce impacts on surrounding neighborhoods.
The city plans to provide regular progress reports to the Waterfront Advisory Board throughout construction and may conduct periodic site visits so board members can observe the work firsthand. When completed, the project will deliver a new bulkhead, rebuilt marina infrastructure and a reconfigured waterfront layout intended to support future development along Fernandina Harbor.